CONTACT
  • THE PROJECT
    About
    • HISTORY
    • COMPLIANCE
    • STP1 TODAY
    • PARTNERS
    Concept & Layout
    Project Progress
    Technology
  • GURNEY WHARF
    A Penang State Project
    Background
    Reclamation
  • COMMUNITY
  • UPDATES
  • FAQ
CONTACT
  • HOME
  • THE PROJECT
    • ABOUT
      • HISTORY
      • COMPLIANCE
      • STP1 TODAY
      • PARTNERS
    • CONCEPT & LAYOUT
    • PROJECT PROGRESS
    • TECHNOLOGY
  • GURNEY WHARF - A Penang State Project
    • BACKGROUND
    • RECLAMATION
  • COMMUNITY
  • UPDATES
    • PRESS RELEASES
    • ANNOUNCEMENTS
  • FAQ

GURNEY WHARF - A Penang State Project

RECLAMATION

  • 2019
  • 2018
  • 2017
  • 2016
Dec 2016
Tong Tu, a Trailer Suction Hopper Dredger (TSHD) with a 20,000m³ capacity, was mobilised in mid-December 2016 to facilitate reclamation works
Nov 2016
Overall view of reclamation works
Nov 2016
Progress of perimeter rock bund
Oct 2016
Loading of rocks for the perimeter rock bund
Aug 2016
Progress of perimeter rock bund